SR120/Union Road Interchange Project
1st Diverging Diamond Interchange (DDI) in California.

The City of Manteca in partnership with Caltrans District 10 and SJCOG are working to improve safety and traffic flow at interchange located at State Route 120 and Union Road. The project will improve safety conditions by constructing new on and off ramps, widening Union Road to 4 lanes between Daniels Street and Lifestyle Street, and providing a Class I shared-use path and Class II bike lanes.

The new interchange reduces conflict points between vehicles and moves traffic more efficiently through the interchange. The DDI is unique in that traffic on the local road is shifted to the left side of the road, before being shifted back to the right. Eliminating any left hand turns through the intersection.  Upgrading to the unique DDI configuration provides significant cost savings and safety benefits for both vehicles and pedestrians.

Union Road is a key crossing of State Route 120 in the City’s bicycle master plan. The new Class I path will provide a 10-foot wide grade-separated trail that eliminates all bicycle/vehicle conflict points within the interchange to provide safe and efficient passage for bicycles, pedestrians, and other non-motorized travel.

Auxiliary lanes will be constructed between Airport Way and Main Street on eastbound and westbound State Route 120 to provide for increased traffic flow during peak times.

 

Project Partners:

Benefits of a
Diverging Diamond Interchange (DDI)

  • Safety is a priority.  This Diverging Diamond Interchange will reduce the number of conflict points from the existing 26 down to 14.  Most importantly, the more severe collision types (crossing/T-bone) are reduced form 10 down to two.

    Existing overpass does not have designated pedestrian or bicycle access. The new interchange will provide a Class I shared-use path and Class II bike lanes. The new Class I path will provide a 10-foot wide grade-separated trail that eliminates all bicycle/vehicle conflict points within the interchange providing safe and efficient passage for bicycles, pedestrians, and other non-motorized travel. 

  • Cost effective solution allows for the project costs to be greatly reduced compared to other interchange types. Also allows for the existing bridge to remain.

  • Improved traffic operations on Union Road. This project will construct auxiliary lanes on State Route 120 from Airport Way to Main Street.

  • Compact footprint by eliminating right of way acquisition.

  • Class I grade separated shared use path improves pedestrian and bicycle mobility. This accomplishes the City’s General Plan goal and closes a significant gap in the pedestrian network.

  • Safety is highly increased with a DDI due to a reduction in collision points from 26 to 14 and separate bicycles and pedestrian lanes.

Funding

Shared Funding for this project is provided by City of Manteca, and San Joaquin Council of Governments.

Construction
Schedule

Project Completion 95%

Project Schedule

June 25, 2019 Groundbreaking Event
July 2019 Construction Begins
November 25, 2020 New DDI opens

Project Notes

  • Delays are anticipated weekdays between 6:00am – 4:00pm on Union Road between Atherton Drive and Daniels Street. Please be aware of increased truck traffic in the area as a result of the interchange improvements.
  • Traffic Detours and Closures will be posted in advance on this website in the Updates Section and the City of Manteca Facebook Page.
  • Work will generally take place between 6 a.m. and 5 p.m. Monday through Friday. Night and/or weekend work may occur as necessary.

Project Hotline: 209.707.3470

Project
Updates

SR 120 Westbound and Eastbound Closures

SR120 Ramp and Highway Closure Alert

Please be advised of the following upcoming closures (weather permitting):

SR 120 Westbound Ramp Closure
Friday, April 24th crews will close the existing westbound ramp at SR 120 and Union Road to construct a new ramp connection to SR 120. The new ramp to westbound SR 120 will be open to traffic no later than April 27th.

SR 120 Westbound Night Closure
Wednesday, April 29 – 9:00pm – 5:00am
Thursday, April 30 – 9:00pm – 4:00am
Detours will direct traffic off SR 120 at Union Road south to Atherton Drive to rejoin SR 120 westbound at Airport Way.

SR 120 Eastbound Night Closure
Tuesday, May 6 to Thursday, May 8 – 9:00pm – 5:00am Nightly
Detours will direct traffic off SR 120 at Airport Way south to Atherton Drive to rejoin SR 120 eastbound at Union Road.

Temporary Closures through the end of December
– Westbound Union Road on-ramp will be closed through December 2020
– Eastbound Union Road off-ramp will be closed through December 2020
Ramp Closure Detour Access to Highway 120 via Airport Way and Main Street

Please expect delays and proceed with caution to ensure the safety of the traveling public and construction crews.

Call the project hotline with any questions or concern and a project team member will get back to you – 209.707-3470.

We apologize in advance for any inconvenience.

April 23rd, 2020|Construction Alerts|

SR 120 Westbound Ramp Closure at Union Road

Closure Dates: April 24 – April 27

Please be advised, Friday, April 24th crews will be closing the existing westbound ramp at SR 120 and Union Road to construct a new ramp connection to SR 120. The new ramp to westbound SR 120 will be open to traffic no later than April 27th.

Temporary Closures through the end of December
– SR 120 Westbound Union Road
– SR 120 Eastbound Union Road
Ramp Closure Detour Access to Highway 120 via Airport Way and Main Street

Please expect delays and proceed with caution to ensure the safety of the traveling public and construction crews.

Call the project hotline with any questions or concern and a project team member will get back to you – 209.707-3470.

We apologize in advance for any inconvenience.

April 20th, 2020|Construction Alerts|

SR 120 Eastbound Ramp at Union Road

Closure Update

Friday, April 17th crews will be closing the existing eastbound on-ramp at SR 120 and Union Road to construct a new on-ramp connection to SR 120. The new on-ramp to eastbound SR 120 will be open to traffic no later than April 20th.

Friday, April 24th crews will be closing the existing westbound off-ramp at SR 120 and Union Road to construct a new off-ramp connection to SR 120. The new off-ramp to eastbound SR 120 will be open to traffic no later than April 27th.

Temporary Closures through the end of December
– Westbound Union Road on-ramp will be closed through December 2020
– Eastbound Union Road off-ramp will be closed through December 2020
Ramp Closure Detour Access to Highway 120 via Airport Way and Main Street

Please expect delays and proceed with caution to ensure the safety of the traveling public and construction crews.

Call the project hotline with any questions or concern and a project team member will get back to you – 209.707-3470.

We apologize in advance for any inconvenience.

April 2nd, 2020|Construction Alerts|

SR 120, Main Street, Union Road, and Airport Road Closure Update

Closure Update – March 11, 2020

Please be advised, Sunday, March 15 through Thursday, March 19, NIGHT crews will be working intermittently on westbound SR120 as well as
on-ramps and off-ramps at Main Street, Union Road, and Airport Road.

Closure Details
Sunday, March 15 through Thursday, March 19
10:00pm to 5:00am
Intermittent closures – Expect delays
– SR120 westbound lane closures
– Westbound Main Street on-ramp
– Westbound Union Road off-ramp
– Westbound Airport Road off-ramp

Temporary Closures through the end of December
– Westbound Union Road on-ramp will be closed through December 2020
– Eastbound Union Road off-ramp will be closed through December 2020
Ramp Closure Detour Access to Highway 120 via Airport Way and Main Street

Please expect delays and proceed with caution to ensure the safety of the traveling public and construction crews.

Call the project hotline with any questions or concern and a project team member will get back to you – 209.707-3470.

We apologize in advance for any inconvenience.

March 11th, 2020|Construction Alerts|

SR 120, Main Street, and Airport Road Closure Update

Closure Update – February 23, 2020

Please be advised, February 23 to February 28 NIGHT crews will be working on eastbound and westbound SR 120 at Union Road for the installation of K-Rail which will create sporadic lane and ramp closures.

Additionally, SR 120 eastbound and westbound closures will occur next week which will result in ramp closures at Union Road, Airport Road, and Main Street.

Lane Closure Details

Sunday, February 23 to Friday, February 28
10:00pm to 5:00am (Sporadic closures)
Westbound off-ramp at Union Road
Eastbound on-ramp from Union Road
Eastbound off-ramp at Main Street
Westbound on-ramp from Main Street
Westbound off-ramp at Airport Road
Eastbound on-ramp from Airport Road

24-hour Closures through the end of December
Westbound Union Road on-ramp will be closed through December 2020
Eastbound Union Road off-ramp will be closed through December 2020
Ramp Closure Detour Access to Highway 120 via Airport Way and Main Street

Please expect delays and proceed with caution to ensure the safety of the traveling public and construction crews.

Call the project hotline with any questions or concern and a project team member will get back to you – 209.707-3470.

We apologize in advance for any inconvenience.

February 21st, 2020|Construction Alerts|

Recent Posts

Categories

JOIN OUR MAILING LIST

Keep Up-To-Date on Project Details

Fill in the form below to be added to our newsletter.

    Get In Touch

    Project Hotline: 209.707.3470

    Send Us A Quick Email

      Go to Top